4

Power Cavern: Work has now begun on

constructing the concrete structure inside the

cavern, which will house the turbine and generator

plus all the ancillary storerooms, offices and

workshops associated with a modern power station.

As mentioned last month this will take about a year

to complete.

For further information on the project see the official website at

www.glendoe.co.uk

These updates are issued monthly and if you are not already receiving them directly

by email and would like to please contact douglas.gilchrist1@btopenworld.com or

if you have any questions or concerns about the project you should contact Douglas

Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by

email.

PDF created with pdfFactory trial version www.pdffactory.com

Glendoe Hydro Electric

issue 13 April 2007

Power Cavern: Excellent progress has been made

carving out the cavern and over 60% of the volume

of rock has now been excavated. The picture below

shows staff just beginning to work on the

transformer bay on the right while straight ahead of

them a huge slab of rock awaits their attention.

The next critical stage in the cavern will be to install

the main beam to support the travelling crane,

PDF created with pdfFactory trial version www.pdffactory.com

1

which will take about 6 weeks to complete. During

this time blasting work in the cavern will necessarily

have to be suspended. The huge beam is made in

situ of reinforced concrete and will be anchored to

the rock face at various points along its 35-metre

length. The crane will be essential for future

maintenance of the heavy equipment in the power

station and will ultimately be rated to lift over 200

tonnes. In the meantime the crane will be used to

complete the final construction of the cavern.

The turbine to be installed as the prime mover to

drive the 100MW generator will be a Pelton turbine

invented by the American, Lester Pelton in the

nineteenth century.

PDF created with pdfFactory trial version www.pdffactory.com

It works by directing water jets on to buckets and

the resulting impulse spins the turbine. The buckets

are mounted in pairs, to keep the forces on the

wheel balanced, as well as to ensure smooth,

efficient momentum transfer of the water jet to the

wheel. The Pelton wheel is most efficient in high

head applications such as here at Glendoe which

will have over 600 metres from the dam down to the

turbine.

Dam: It is now excavated down to foundation level

along 60% of the dam’s 1000 metre length. Work

has just begun placing the rockfill to form the

embankment or what most people would recognise

as the actual dam. The rockfill is obtained from a

borrow pit established within the reservoir area

which will eventually be flooded. The picture below

shows the scale of the work here.

PDF created with pdfFactory trial version www.pdffactory.com

Headrace Tunnel: Boring of the headrace tunnel

continues to exceed target with over 560 metres of

tunnel now completed and “Eliza Jane” and her

team are well ahead of programme.

Aqueduct Tunnel: Good progress is being made

here as well and the team has now completed over

600 metres from west to east. A second portal was

created last month half way along the 8km tunnel

with this team working back east to west. And now

work is just starting on creating a third portal beside

the new bridge over the Allt Creag Chomaich river

completed last month and this team will also work

from west to east.

Visit to Site: SSE is planning to hold a tour round

the site for interested members of the public on the

afternoon of Tuesday 10 July 2007. Unfortunately

space is limited and for safety reasons the site can

only cope with a maximum of 30 visitors at one

time. However if it is over-subscribed consideration

will be given to holding a similar event later on in

the year. If you would like a place on the tour

please complete and return the attached application

– one application per person please -and return it

to the address shown.

PDF created with pdfFactory trial version www.pdffactory.com

Application to attend SSE open day at Glendoe Hydro Construction Project site,

Fort Augustus on Tuesday 10 July 2007 at 1.30pm

Name …………………………………………………. Age ……..

(if under 18)

Address ………………………………………………….

………………………………………………….

………………………………………..

………………………………… Post Code ………..

Daytime tel no. …………………………………..

Email address ……………………………………………..

Please return completed forms to: Douglas Gilchrist, Glendoe Hydro Construction Project,

Ingleside, Belladrum, Beauly, Inverness IV4 7BA to be received no later than Thursday 31 May

2007

Application to attend SSE open day at Glendoe Hydro Construction Project site,

Fort Augustus on Tuesday 10 July 2007 at 1.30pm

Name …………………………………………………. Age ……..

(if under 18)

Address ………………………………………………….

………………………………………………….

………………………………………..

………………………………… Post Code ………..

Daytime tel no. …………………………………..

Email address ……………………………………………..

Please return completed forms to: Douglas Gilchrist, Glendoe Hydro Construction Project,

Ingleside, Belladrum, Beauly, Inverness IV4 7BA to be received no later than Thursday 31 May

2007

For further information see the official website at

www.glendoe.co.uk

These updates are issued monthly and if you are not already receiving them

directly by email and would like to please contact

douglas.gilchrist1@btopenworld.com or if you have any questions or

concerns about the project you should contact Douglas Gilchrist, the

Community Liaison Officer at 01463 741322 or 07770 408083 or by email.

issue 12 March 2007

Power Cavern: This is where the power station will

be located and already over 85% of the roof of the

cavern has been exposed.

Some idea of the complexity of the cavern can be

gauged from the drawing above which shows a

section through the 30 metre high cavern with the

huge 100MW generator shown (faintly in orange)

sitting on top of the giant turbine. The main access

1

PDF created with pdfFactory trial version www.pdffactory.com

tunnel completed last month can be seen at the top

left of the drawing.

Road: The temporary road from the dam east over

the plateau has now reached over half way. The

picture below shows work beginning on the bridge

to take the road across the Allt Creag Chomaich

river. This bridge will remain as a permanent fixture

but the road from the west up to it will be removed

once the project is completed.

2

PDF created with pdfFactory trial version www.pdffactory.com

Headrace Tunnel: Boring of the headrace tunnel

began last month and already the tunnel-boring

machine “Eliza Jane” has had a record week

completing over 260 metres of tunnel with a

staggering 74 metres in one exceptional day. The

headrace tunnel will be used to feed water down to

drive the turbine. At present “Eliza Jane” and her

team are well ahead of schedule but there is a long

way to go.

Aqueduct Tunnel: Good progress is being made

here as well with the drill and blast team now over

400 metres in moving from west to east. A second

portal is being created half way along the 8km

tunnel and this team will work east to west.

Dam: Work on the dam continued, but winter

weather has caused some delay. With the coming

of longer daylight hours and improved weather,

progress will improve. Assembly of concrete

batching equipment at the dam site is complete and

this will permit up to 60 cubic meters of concrete to

be made in an hour.

Community Benefit Fund: An agreement has

been signed earlier this month that will enable funds

to be distributed to the local communities. The

Glendoe community fund will provide:

· A £60,000 a year fixed sum.

PDF created with pdfFactory trial version www.pdffactory.com

• A variable sum, which is calculated in relation to

the amount of power the scheme generates each

year.

• A separate £300,000 energy efficiency package.

Decisions on how the money is spent will be made

by the Fort Augustus and Glenmoriston Community

Company and Stratherrick and Foyers Community

Trust, who will be supported by the Scottish

Community Foundation, a charity which specialises

in distributing funding such as this.

.

The photograph above shows Rev Dr Adrian

Varwell of Fort Augustus and Glenmoriston

Community Council with Alex Sutherland and JW

Campbell of Stratherrick and Foyers Community

Trust signing the historic document.

PDF created with pdfFactory trial version www.pdffactory.com

These updates are issued monthly and if you are not already

receiving them directly by email and would like to please contact

douglas.gilchrist1@btopenworld.com or if you have any

questions or concerns about the project you should contact

Douglas Gilchrist, the Community Liaison Officer at

01463741322 or 07770408083 or by email

Glendoe Hydro Electric

issue 11 February 2007

Tunnels: The tunnel boring machine, “Eliza Jane”

completed the tailrace tunnel right on schedule at

the end of January and has already moved on to

the longer task of boring the headrace tunnel.

The photograph above shows the route of the steep

6.2km tailrace tunnel as it climbs up to connect with

PDF created with pdfFactory trial version www.pdffactory.com

2

the dam. The tunnel will take a full year to

complete. Meanwhile the main access tunnel into

the power cavern was completed ahead of schedule

last month.

Power Cavern: Where the tailrace and the access

tunnels meet the huge power cavern will be carved

out inside the mountain.

The picture above shows this work just beginning at

roof level of the cavern. Excavation of the 50 metre

long by 30 metre high by 20 metre wide cavern will

be completed within 6 months and then construction

will commence of the reinforced concrete power

house which will house the 100MW generator and

turbine plus all the ancillary equipment needed in a

modern power station.

PDF created with pdfFactory trial version www.pdffactory.com

3

Dam: Work on the dam continued last month but

the inevitable snow and frost combined to slow

things down.

The river diversion culvert is making reasonable

progress and is on target for diverting the River

Tarff in the summer. This diversion will allow work

to continue to complete the dam along its full length.

Then once the dam is complete the diversion will be

shut off and the new reservoir filled up ready to

supply water to power the turbine. The diversion

will then be used to provide compensation water

down the river as part of the environmental

provision.

Trials are also well under way testing the rock

produced from the on–site borrow pit, to establish

optimum compaction for construction of the dam

embankment.

Roads: The road from the dam to Intake 8 has now

been completed and is about a quarter of the way

across the plateau where the fourteen river intakes

are situated. It is worth noting that the length of

road from the reservoir area completed to date will

in fact be removed and the ground restored once

the construction phase of the project is complete.

PDF created with pdfFactory trial version www.pdffactory.com

4

Concrete Batching Plant: A second batching

plant has been established on the site up at the

dam and is capable of producing an impressive 60

cubic metres of concrete an hour. To get some

idea of the scale more than 140,000 cubic metres of

concrete will be needed on the site.

Aqueduct Tunnel: Drilling and blasting of the

aqueduct tunnel continues and just over 250 metres

of the 7 km tunnel have been completed. This

tunnel will be used to feed water from the various

intakes into the reservoir. Each tunnelling squad

can complete up to 50 metres a week. To meet the

programme and complete the tunnel by March next

year engineers will need to employ additional

squads working simultaneously on up to five faces.

For further information see the official website at

www.glendoe.co.uk

These updates are issued monthly and if you are not already

receiving them directly by email and would like to please contact

douglas.gilchrist1@btopenworld.com or if you have any

questions or concerns about the project you should contact

Douglas Gilchrist, the Community Liaison Officer at

01463741322 or 07770408083 or by email

PDF created with pdfFactory trial version www.pdffactory.com

issue 10 January 2007

Tunnels: Work continued over the Christmas and

New Year holiday period with a skeleton staff but

nevertheless they have made very good progress.

The drilling and blasting of the main access tunnel

will be completed by the middle of this month at

which point work will begin on creating the huge

power cavern which will measure 50 metres long by

20 metres wide by 30 metres high. This will house

the giant turbine and generator. “Eliza Jane” is not

far behind and should reach the power cavern by

the end of the month. The photograph below

shows the drill for setting the explosives on the

aqueduct tunnel up beyond the dam.

PDF created with pdfFactory trial version www.pdffactory.com

2

Internet Conection: Just before Christmas SSE

set up an internet connection available to the public

in the Spar shop attached to the Great Glen Filling

Station in Fort Augustus. No computer expertise is

required as the easy-to-use system employs a

“touch-screen” system that enables the viewer to

navigate around the site and tap into a wealth of

information about the scheme. The picture below

shows visitor Jean Plater from Buckinghamshire

browsing through the website.

PDF created with pdfFactory trial version www.pdffactory.com

3

Camp Site: The second camp up at the dam site is

now fully operational and will be able to cater for

over a 100 staff working on the dam, the road and

the aqueduct.

Dam: Work has now begun pouring concrete for

the dam foundation and preparing an area to carry

out tests to establish the degree of compaction of

the rock fill. The photograph below shows the first

pour of concrete.

PDF created with pdfFactory trial version www.pdffactory.com

4

Roads: Staff are making excellent progress on the

temporary access road from the dam east across

the plateau. A quarry is currently being established

in the middle of the proposed reservoir to supply the

rock for the road. This road will be used during the

construction of the aqueduct tunnel and pipeline

and also to establish the numerous river intakes.

For further information see the official website at

www.glendoe.co.uk

These updates are issued monthly and if you are not already

receiving them directly by email and would like to please contact

douglas.gilchrist1@btopenworld.com or if you have any

questions or concerns about the project you should contact

Douglas Gilchrist, the Community Liaison Officer at

01463741322 or 07770408083 or by email

PDF created with pdfFactory trial version www.pdffactory.com

1

Glendoe Hydro Electric

issue 9 December 2006

Blessing of the Tunnel Works: Now that work

has begun on all three of the tunnels on the project

a ceremony was held on site on the 4th of

December 2006 to name and bless the tunnels in

the name of St Barbara, the patron saint of miners.

On a wet and windy hillside an audience of over

120 invited guests and staff attended the ceremony

led by Father Michael Savage. Local minister Dr

Adrian Varwell read a passage from the Old

Testament (Job verse 28) followed by Father

Ryszathe Swider who repeated the prayer in Polish.

.

PDF created with pdfFactory trial version www.pdffactory.com

Glendoe Hydro Electric

issue 8 November 2006

Tunnel Boring Machine (TBM): “Eliza Jane ” is

getting into her stride and in the last month more

than doubled the length of the tailrace tunnel. Full

commissioning tests are still going on and it will be

another month or so before she is up to full speed.

Nevertheless she has been cutting through an

impressive 100 metres of finished tunnel a week.

Loch

Ness

Tailrace

Outfall

Main

Access

Tunnel

Powerhouse

Cavern

Generator

Pelton wheel

Turbine

U/G

Transformer

HV Cables 100MW LV

BusBars

Power

Tunnel

Max flow rate = 18.7m3/sec

Static Head (604.3m) - Losses

= Net Head

Dam

Intake

tower Reservoir Aqueduct

Glendoe HEP Scheme

Spillway

shaft

PDF created with pdfFactory trial version www.pdffactory.com

2

Access Tunnel: Drilling and blasting of the access

tunnel is well on target with more than half of the

1200 metre tunnel now excavated. Work will then

begin carving out the power station cavern 250

metres below ground level, which will house the

giant turbine and generator as shown in the

diagram on the previous page.

Aqueduct Tunnel: Meanwhile, at the other end of

the project, work has started on the aqueduct

tunnel, which will ultimately be used to feed water

into the reservoir.

The picture above shows work just beginning to

form the portal, or entrance to the 7km tunnel. The

PDF created with pdfFactory trial version www.pdffactory.com

3

tunnel is programmed for completion in the spring of

2008.

Dam: Work is well underway excavating down to

the foundation rock along approximately a third of

the length of the 1000 metre dam. The picture

below shows progress on the bottom outlet from the

dam. This is at the base of the dam and will be

used to release water from the reservoir into the

River Tarff (just visible on the right of the picture) on

the rare occasions when it would be necessary to

drain the reservoir.

PDF created with pdfFactory trial version www.pdffactory.com

4

Camp Site: Work is also well in hand for the

second camp up near the dam. This will be used to

accommodate staff working on the dam and

aqueduct tunnel. Occupation of the camp will begin

later this month.

These updates are issued monthly and if you are not already

receiving them directly by email and would like to please contact

douglas.gilchrist1@btopenworld.com or if you have any

questions or concerns about the project you should contact

Douglas Gilchrist, the Community Liaison Officer at

01463741322 or 07770408083 or by email

PDF created with pdfFactory trial version www.pdffactory.com

1

Glendoe Hydro Electric

issue 7 October 2006

Tunnel Boring Machine (TBM): At the very end of

last month “Eliza Jane ” was finally commissioned

on time and took the first tentative cuts at the rock

face to begin her 6-month journey through the hill to

complete the 2km tailrace tunnel.

The photograph above shows the back of the

machine as it prepares to disgorge the rock spoil on

PDF created with pdfFactory trial version www.pdffactory.com

2

to the conveyor belt and out to the holding area.

Once she is fully up to speed she is expected to

produce at least 25 metres of finished tunnel every

day.

Also visible on the photograph is the ventilation duct

through which huge fans suck in vital fresh air for

the staff working deep in the tunnel. These fans

have to operate round the clock and so that their

noise isn’t a nuisance for people in the surrounding

area they have been located well inside the tunnel.

Hochtief have just taken delivery of the first of

several of these multi service vehicles, which have

been purpose-built to supply equipment and

materials into the tunnel.

PDF created with pdfFactory trial version www.pdffactory.com

3

Conveyor Belt: The conveyor belt, which carries

the rock out of the tunnel has also just been

commissioned and will shortly be covered over in its

corrugated iron housing. The photograph below

shows the holding area up behind the main offices

and camp where the rock will be stored before

being used at various locations throughout the site.

Cable Laying: Balfour Beatty have now left site

having completed the first stage of the cable works

but will be back probably towards the end of next

year for the final stage. Meanwhile specialised

contractors will shortly begin excavations to

establish the ground conditions for the cable ducts

under the canal and the River Oich.

PDF created with pdfFactory trial version www.pdffactory.com

4

Dam: Work on the second camp area up at the

dam site is progressing well with several of the

buildings already up. The camp should be ready for

occupation sometime next month. Over two

hundred staff will eventually be working on the dam

and the associated aqueduct of which a hundred

and twenty or so will be housed in the camp.

These updates are issued monthly and if you are not already

receiving them directly by email and would like to please contact

douglas.gilchrist1@btopenworld.com or if you have any

questions or concerns about the project you should contact

Douglas Gilchrist, the Community Liaison Officer at

01463741322 or 07770408083 or by email

PDF created with pdfFactory trial version www.pdffactory.com

02.10.06

Kenyan athletes won both the men's and women's marathons at this year's Baxters Loch Ness Marathon and Festival of Running yesterday.

Just eight seconds separated the first and second runners in the men's marathon, which took place along the south side of Loch Ness and on to the Inverness Queens Park Stadium.

Zakary Kihara, of Kenya, beat last year's winner Simon Pride, of Fochabers, into second place with a time of two hours, 22 minutes and 17 seconds.

Mr Pride, who also won the race in 2004, completed the course in two hours, 22 minutes and 25 seconds.

Third was Jamie Reid, of Ronhill, Cambuslang, near Glasgow, in a time of two hours, 24 minutes and four seconds.

A total of 5,600 runners of all ages and abilities took part in the day, sponsored by Baxters Food Group, putting this year's entry about 1,000 up on the previous record.

The full marathon attracted 2,073 runners, while 2,450 took part in the Baxters River Ness 10k Run and there were almost 1,000 entries in the Baxters River Ness 5k Fun Run.

The women's marathon was hotly contested, with Kenya's Hellen Cherono winning in a time of two hours, 46 minutes and 54 seconds. Second was Krystyna Kuta, of Poland, with two hours, 47 minutes and 30 seconds, followed by Jennifer Maclean, of City of Edinburgh Athletic Club, with two hours, 58 minutes and 57 seconds.

Race director Malcolm Sutherland said the event not only attracted elite Scottish, international and club runners, but was massively popular with amateurs, joggers and people running for charity.

Mr Sutherland said: "The event has been an outstanding success and the weather conditions tested all runners?. He said the event also provided a massive boost to the local economy. The most recent figures available show that £958,100 was spent on accommodation, food and activities during the 2004 festival

I am pleased to announce a £20,000.00 upgrade at Loch Ness Gun Club in early October. This is a continuation of facility upgrades including new toilet block, new disabled access ramp to club house and a further £14000.00 of upgarding of equipment over the last year.

This new upgrade is privately financed and is updating one of the Olympic Trap ranges at the ground. This will see only the second such range in Scotland, the other being in Ayrshire. Once completed the range will be completely automatic dispensing with the need of manual operation.

This will significantly add to the facilities we currently have and expect a substantial increase in visitors and competitors to the ground at Bhlaraidh, Glenmoriston.

We will be open this Saturday (23rd) for the Duncan Macdonell Memorial Shoot, 100 DTL and next Wednesday from 3pm to 7pm for a club practice and Saturday (30th) for coaching and practice with ex British Shooting Champion Mike Milne.

Anyone is welcome when we are open and I am only too happy to personally show visitors and locals alike round the facilities.

We will be closed during the month of October but will be open every Saturday from the 4th of November onwards. We also welcome anyone who hasnt shot before to come and give it a try with experienced coaches available every day apart from a Sunday by prior appointment.

For more information I can be contacted on 01320 340341, 07770 800910 or dagillies@hotmail.com. The web address is www.lochnessgunclub.co.uk

Regards

David Gillies

Director

Loch Ness Gun Club Ltd

Achlain Estates Limited

Glenmoriston

Inverness

IV63 7YN

tel: +44 (0) 1320 340341

fax: +44 (0) 1320 340255

email: david@achlainestates.co.uk

website: www.achlainestates.co.uk

1

Glendoe Hydro Electric

issue 6 September 2006

Traffic Management: The temporary traffic lights

on the B862 will be removed in the near future and

priority will return to traffic on the B862. There have

however been a number of complaints by residents

that traffic on the B862 and B851 has not only

increased dramatically since the project began but

also the standard of driving has caused concern.

Highland Council has been monitoring the volume

of traffic and will be releasing the figures shortly. In

the meantime Hochtief has written to all their subcontractors

reminding them of their contractual

obligation to use the A82 as the main access to the

site. Hochtief has also erected signs at critical

locations on the B862 and B851 advising there is no

access to the site from these roads.

Tunnel Boring Machine (TBM): Work continues

commissioning “Eliza Jane” and she is expected to

start work in earnest at the end of September.

Progress will depend on rock conditions but she

should be able to get through somewhere in the

region of 25 metres of finished tunnel a day. This

will mean the 2km tailrace tunnel up to the cavern

power station will be finished around March 2007.

PDF created with pdfFactory trial version www.pdffactory.com

2

A further 12 months of boring through the mountain

will be needed for the 6km headrace tunnel from the

power station up to the dam.

Conveyor Belt: The huge volume of rock that

“Eliza Jane” throws out will be taken by conveyor

belt up to the designated disposal area. The rock

will be used for construction and future

maintenance of the roads. Work is well under way

with erecting the conveyor belt and the photograph

below shows the belt as it passes below the B862.

Cable Laying: Balfour Beatty have virtually

completed the first stage of the cable works and will

return in a year or so to install the 132,000 volt

cable from the power station up to the existing

PDF created with pdfFactory trial version www.pdffactory.com

3

Auchterawe substation. Detailed site investigations

are being carried out to establish the ground

conditions for the cable ducts under the canal and

the River Oich.

Dam: The rock for constructing the dam will be

produced from a quarry currently being created

near the dam site. A second work camp is also

being established here for over a 100 staff who will

be working on the dam and the aqueduct feeding

water into the proposed reservoir. The photograph

below shows progress with the new road up to the

dam site.

PDF created with pdfFactory trial version www.pdffactory.com

4

Community Event: This was held on 16 August in

Kilchuimen Academy and over 120 locals visited the

exhibition and heard progress on the project to

date. Afterwards a number stayed on to ask

questions and share in some light refreshments.

The photograph below shows some of those who

attended.

These updates are issued monthly and if you are not already

receiving them directly by email and would like to please contact

douglas.gilchrist1@btopenworld.com or if you have any

questions or concerns about the project you should contact

Douglas Gilchrist, the Community Liaison Officer at

01463741322 or 07770408083 or by email

PDF created with pdfFactory trial version www.pdffactory.com

1

Glendoe Hydro Electric

issue 5 August 2006

Camp: The move up to the camp is almost

complete with only the canteen to be re-sited, which

should happen by the end of August. Of the 250 or

so staff on site around a 100 are now resident in the

camp. Hochtief operate a bus service for staff from

the camp down to the village.

Blasting: There have been a large number of

complaints about the disturbance the blasting is

causing in the village. Hochtief have explained that

they try whenever possible not to blast between

11.00pm and 7.00am. However unfortunately there

are occasions when it is not possible to avoid these

times. When the charges have been set and there

is a delay (for example because of a miss-fire) then

they have no alternative for safety and other

reasons but to carry through with the operation.

The good news is that this particular blasting

programme will be finished by mid August.

PDF created with pdfFactory trial version www.pdffactory.com

2

Traffic Management: Work on the B862 from the

bridge just beyond the Abbey up to the site

entrance has now been completed. The road

verges have been strengthened and a 30mph

speed limit introduced between the camp entrance

and beyond the entrance to the access tunnel. In

addition some of the ditches have been cleared to

improve drainage and also undergrowth has been

cut back to improve sight lines.

Tunnel Boring Machine (TBM): “Eliza Jane” has

now been delivered to site and is currently being

assembled ready to start drilling the tailrace tunnel

in September. The huge scale of the machine can

be grasped from the recent photograph below

where the two men on top of it can just be made

out.

PDF created with pdfFactory trial version www.pdffactory.com

3

A large white gantry crane has also been

assembled, which is visible from across Loch Ness

and will be used to load heavy materials and

equipment on to special multi-service vehicles to

supply “Eliza Jane”. This crane, shown in the

photograph below, will be removed when the tunnel

is complete.

Installation of the conveyor belt, which will be used

to take the spoil from “Eliza Jane” up to the storage

area behind the camp is also under way and will be

ready to go for the end of August.

Cable Laying: As mentioned in last month’s

bulletin this first stage of the cable laying

programme is almost complete. However during

August a detailed site investigation will be carried

PDF created with pdfFactory trial version www.pdffactory.com

4

out to establish the ground conditions for the cable

ducts under the canal and the River Oich.

Dam: Trial pits have now been excavated to

establish the foundation conditions for the dam,

which will be laid in August. The new road up to the

dam site is almost finished and survey work is

under way for the tunnels and aqueduct to supply

the reservoir.

Community Event: This has been planned for

Wednesday, 16 August, starting at 5pm at

Kilchuimen Academy. There will be an exhibition,

followed by a presentation at around 7.30pm and

the event will conclude with a canapι reception

from 8pm. The event will be widely publicised

locally and all local people will be welcome to

attend.

Communication: Hochtief have created a 24 hour

Emergency Hotline

Tel: 01456 450950 or if out of hours please call:

07867 973 926 or 07717 574 289

These updates are issued monthly and if you are not already

receiving them directly by email and would like to please contact

douglas.gilchrist1@btopenworld.com or if you have any

questions or concerns about the project you should contact

Douglas Gilchrist, the Community Liaison Officer at

01463741322 or 07770408083 or by email

PDF created with pdfFactory trial version www.pdffactory.com

Glendoe Hydro Electric Bulletin

issue 4 July 2006

Camp: Some of the workforce have moved up to the camp and this will continue throughout the coming weeks. The move could however be delayed because of a problem with the building warrant.

Recruitment: Hochtief took part in a “Meet the Buyer” workshop at the end of June. This was organised by Highlands & Islands Enterprise and enabled over 40 local contractors and suppliers to pitch their wares.

Blasting: Surface blasting is now complete at the tailrace tunnel with the tunnel itself now reaching nearly 100 metres into the hillside. A large blast at 4.00am in the morning towards the end of June caused a number of complaints. The blast was exceptionally loud because it was at the point where the access and tailrace tunnels meet and so there was effectively double the size of blast expelled from the access tunnel.

Cable Laying: Balfour Beatty Power Networks have completed the first stage of 33,000 volt and 11,000 volt cable laying i.e. from the Golf Course up to the site. The reinstatement of the track will be completed by mid July. The second stage will be to install ducts from the Golf Course up to the existing substation at Auchteraw, which should be complete by mid September. The crossing underneath the canal will be done using a directional drilling technique. Next year Balfour Beatty will return to install the 132,000 volt cable from the site through the ducts to Auchteraw

Traffic Management: Part of the B862 road from the bridge up to the site has been widened to ease traffic congestion and will be tarred in early July. Once the road has been white-lined it should provide route for pedestrians.

Communication:

• SSE are currently exploring setting up a dedicated website within the village and some way to make it available to visitors and residents alike.

• An A5 size 16-page colour brochure is also being published which will be available to visitors and residents to take away and will explain the project.

• Preparations are also under way for a visit to the site early in August. The invitation will be extended to all members of the local communities who will be able to meet members of the project team along with representatives of the Scottish Community Foundation who it is hoped will help with distribution of the Community Benefit Fund. Members of SSE’s energy efficiency team will also be on hand to offer advice. At that time it is expected that the huge tunnel boring machine (TBM) will have been assembled and it may be possible for a lucky few to get a trip down to see it. The TBM has been named “Eliza Jane” following a competition among Kilchuimen Primary School pupils.

Site Works: The new road up to the site of the dam is well under way and work on the dam itself is due to begin in August. The 33/11kV transformer was installed in mid-June and is currently undergoing tests prior to commissioning. The transformer will be used to supply power into the site but once the power station comes on stream in 2009 will be used to support the village distribution network and should ultimately allow removal of Markethill substation on the burial ground road.

These updates will be issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by email