| |
4 Power Cavern: Work has now begun on constructing the concrete structure inside the cavern, which will house the turbine and generator plus all the ancillary storerooms, offices and workshops associated with a modern power station. As mentioned last month this will take about a year to complete. For further information on the project see the official website at www.glendoe.co.uk These updates are issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by email. PDF created with pdfFactory trial version www.pdffactory.com Glendoe Hydro Electric issue 13 April 2007 Power Cavern: Excellent progress has been made carving out the cavern and over 60% of the volume of rock has now been excavated. The picture below shows staff just beginning to work on the transformer bay on the right while straight ahead of them a huge slab of rock awaits their attention. The next critical stage in the cavern will be to install the main beam to support the travelling crane, PDF created with pdfFactory trial version www.pdffactory.com 1 which will take about 6 weeks to complete. During this time blasting work in the cavern will necessarily have to be suspended. The huge beam is made in situ of reinforced concrete and will be anchored to the rock face at various points along its 35-metre length. The crane will be essential for future maintenance of the heavy equipment in the power station and will ultimately be rated to lift over 200 tonnes. In the meantime the crane will be used to complete the final construction of the cavern. The turbine to be installed as the prime mover to drive the 100MW generator will be a Pelton turbine invented by the American, Lester Pelton in the nineteenth century. PDF created with pdfFactory trial version www.pdffactory.com It works by directing water jets on to buckets and the resulting impulse spins the turbine. The buckets are mounted in pairs, to keep the forces on the wheel balanced, as well as to ensure smooth, efficient momentum transfer of the water jet to the wheel. The Pelton wheel is most efficient in high head applications such as here at Glendoe which will have over 600 metres from the dam down to the turbine. Dam: It is now excavated down to foundation level along 60% of the dams 1000 metre length. Work has just begun placing the rockfill to form the embankment or what most people would recognise as the actual dam. The rockfill is obtained from a borrow pit established within the reservoir area which will eventually be flooded. The picture below shows the scale of the work here. PDF created with pdfFactory trial version www.pdffactory.com Headrace Tunnel: Boring of the headrace tunnel continues to exceed target with over 560 metres of tunnel now completed and Eliza Jane and her team are well ahead of programme. Aqueduct Tunnel: Good progress is being made here as well and the team has now completed over 600 metres from west to east. A second portal was created last month half way along the 8km tunnel with this team working back east to west. And now work is just starting on creating a third portal beside the new bridge over the Allt Creag Chomaich river completed last month and this team will also work from west to east. Visit to Site: SSE is planning to hold a tour round the site for interested members of the public on the afternoon of Tuesday 10 July 2007. Unfortunately space is limited and for safety reasons the site can only cope with a maximum of 30 visitors at one time. However if it is over-subscribed consideration will be given to holding a similar event later on in the year. If you would like a place on the tour please complete and return the attached application one application per person please -and return it to the address shown. PDF created with pdfFactory trial version www.pdffactory.com Application to attend SSE open day at Glendoe Hydro Construction Project site, Fort Augustus on Tuesday 10 July 2007 at 1.30pm Name . Age .. (if under 18) Address . . .. Post Code .. Daytime tel no. .. Email address .. Please return completed forms to: Douglas Gilchrist, Glendoe Hydro Construction Project, Ingleside, Belladrum, Beauly, Inverness IV4 7BA to be received no later than Thursday 31 May 2007 Application to attend SSE open day at Glendoe Hydro Construction Project site, Fort Augustus on Tuesday 10 July 2007 at 1.30pm Name . Age .. (if under 18) Address . . .. Post Code .. Daytime tel no. .. Email address .. Please return completed forms to: Douglas Gilchrist, Glendoe Hydro Construction Project, Ingleside, Belladrum, Beauly, Inverness IV4 7BA to be received no later than Thursday 31 May 2007 For further information see the official website at www.glendoe.co.uk These updates are issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463 741322 or 07770 408083 or by email. issue 12 March 2007 Power Cavern: This is where the power station will be located and already over 85% of the roof of the cavern has been exposed. Some idea of the complexity of the cavern can be gauged from the drawing above which shows a section through the 30 metre high cavern with the huge 100MW generator shown (faintly in orange) sitting on top of the giant turbine. The main access 1 PDF created with pdfFactory trial version www.pdffactory.com tunnel completed last month can be seen at the top left of the drawing. Road: The temporary road from the dam east over the plateau has now reached over half way. The picture below shows work beginning on the bridge to take the road across the Allt Creag Chomaich river. This bridge will remain as a permanent fixture but the road from the west up to it will be removed once the project is completed. 2 PDF created with pdfFactory trial version www.pdffactory.com Headrace Tunnel: Boring of the headrace tunnel began last month and already the tunnel-boring machine Eliza Jane has had a record week completing over 260 metres of tunnel with a staggering 74 metres in one exceptional day. The headrace tunnel will be used to feed water down to drive the turbine. At present Eliza Jane and her team are well ahead of schedule but there is a long way to go. Aqueduct Tunnel: Good progress is being made here as well with the drill and blast team now over 400 metres in moving from west to east. A second portal is being created half way along the 8km tunnel and this team will work east to west. Dam: Work on the dam continued, but winter weather has caused some delay. With the coming of longer daylight hours and improved weather, progress will improve. Assembly of concrete batching equipment at the dam site is complete and this will permit up to 60 cubic meters of concrete to be made in an hour. Community Benefit Fund: An agreement has been signed earlier this month that will enable funds to be distributed to the local communities. The Glendoe community fund will provide: · A £60,000 a year fixed sum. PDF created with pdfFactory trial version www.pdffactory.com A variable sum, which is calculated in relation to the amount of power the scheme generates each year. A separate £300,000 energy efficiency package. Decisions on how the money is spent will be made by the Fort Augustus and Glenmoriston Community Company and Stratherrick and Foyers Community Trust, who will be supported by the Scottish Community Foundation, a charity which specialises in distributing funding such as this. . The photograph above shows Rev Dr Adrian Varwell of Fort Augustus and Glenmoriston Community Council with Alex Sutherland and JW Campbell of Stratherrick and Foyers Community Trust signing the historic document. PDF created with pdfFactory trial version www.pdffactory.com These updates are issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by email Glendoe Hydro Electric issue 11 February 2007 Tunnels: The tunnel boring machine, Eliza Jane completed the tailrace tunnel right on schedule at the end of January and has already moved on to the longer task of boring the headrace tunnel. The photograph above shows the route of the steep 6.2km tailrace tunnel as it climbs up to connect with PDF created with pdfFactory trial version www.pdffactory.com 2 the dam. The tunnel will take a full year to complete. Meanwhile the main access tunnel into the power cavern was completed ahead of schedule last month. Power Cavern: Where the tailrace and the access tunnels meet the huge power cavern will be carved out inside the mountain. The picture above shows this work just beginning at roof level of the cavern. Excavation of the 50 metre long by 30 metre high by 20 metre wide cavern will be completed within 6 months and then construction will commence of the reinforced concrete power house which will house the 100MW generator and turbine plus all the ancillary equipment needed in a modern power station. PDF created with pdfFactory trial version www.pdffactory.com 3 Dam: Work on the dam continued last month but the inevitable snow and frost combined to slow things down. The river diversion culvert is making reasonable progress and is on target for diverting the River Tarff in the summer. This diversion will allow work to continue to complete the dam along its full length. Then once the dam is complete the diversion will be shut off and the new reservoir filled up ready to supply water to power the turbine. The diversion will then be used to provide compensation water down the river as part of the environmental provision. Trials are also well under way testing the rock produced from the onsite borrow pit, to establish optimum compaction for construction of the dam embankment. Roads: The road from the dam to Intake 8 has now been completed and is about a quarter of the way across the plateau where the fourteen river intakes are situated. It is worth noting that the length of road from the reservoir area completed to date will in fact be removed and the ground restored once the construction phase of the project is complete. PDF created with pdfFactory trial version www.pdffactory.com 4 Concrete Batching Plant: A second batching plant has been established on the site up at the dam and is capable of producing an impressive 60 cubic metres of concrete an hour. To get some idea of the scale more than 140,000 cubic metres of concrete will be needed on the site. Aqueduct Tunnel: Drilling and blasting of the aqueduct tunnel continues and just over 250 metres of the 7 km tunnel have been completed. This tunnel will be used to feed water from the various intakes into the reservoir. Each tunnelling squad can complete up to 50 metres a week. To meet the programme and complete the tunnel by March next year engineers will need to employ additional squads working simultaneously on up to five faces. For further information see the official website at www.glendoe.co.uk These updates are issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by email PDF created with pdfFactory trial version www.pdffactory.com issue 10 January 2007 Tunnels: Work continued over the Christmas and New Year holiday period with a skeleton staff but nevertheless they have made very good progress. The drilling and blasting of the main access tunnel will be completed by the middle of this month at which point work will begin on creating the huge power cavern which will measure 50 metres long by 20 metres wide by 30 metres high. This will house the giant turbine and generator. Eliza Jane is not far behind and should reach the power cavern by the end of the month. The photograph below shows the drill for setting the explosives on the aqueduct tunnel up beyond the dam. PDF created with pdfFactory trial version www.pdffactory.com 2 Internet Conection: Just before Christmas SSE set up an internet connection available to the public in the Spar shop attached to the Great Glen Filling Station in Fort Augustus. No computer expertise is required as the easy-to-use system employs a touch-screen system that enables the viewer to navigate around the site and tap into a wealth of information about the scheme. The picture below shows visitor Jean Plater from Buckinghamshire browsing through the website. PDF created with pdfFactory trial version www.pdffactory.com 3 Camp Site: The second camp up at the dam site is now fully operational and will be able to cater for over a 100 staff working on the dam, the road and the aqueduct. Dam: Work has now begun pouring concrete for the dam foundation and preparing an area to carry out tests to establish the degree of compaction of the rock fill. The photograph below shows the first pour of concrete. PDF created with pdfFactory trial version www.pdffactory.com 4 Roads: Staff are making excellent progress on the temporary access road from the dam east across the plateau. A quarry is currently being established in the middle of the proposed reservoir to supply the rock for the road. This road will be used during the construction of the aqueduct tunnel and pipeline and also to establish the numerous river intakes. For further information see the official website at www.glendoe.co.uk These updates are issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by email PDF created with pdfFactory trial version www.pdffactory.com 1 Glendoe Hydro Electric issue 9 December 2006 Blessing of the Tunnel Works: Now that work has begun on all three of the tunnels on the project a ceremony was held on site on the 4th of December 2006 to name and bless the tunnels in the name of St Barbara, the patron saint of miners. On a wet and windy hillside an audience of over 120 invited guests and staff attended the ceremony led by Father Michael Savage. Local minister Dr Adrian Varwell read a passage from the Old Testament (Job verse 28) followed by Father Ryszathe Swider who repeated the prayer in Polish. . PDF created with pdfFactory trial version www.pdffactory.com Glendoe Hydro Electric issue 8 November 2006 Tunnel Boring Machine (TBM): Eliza Jane is getting into her stride and in the last month more than doubled the length of the tailrace tunnel. Full commissioning tests are still going on and it will be another month or so before she is up to full speed. Nevertheless she has been cutting through an impressive 100 metres of finished tunnel a week. Loch Ness Tailrace Outfall Main Access Tunnel Powerhouse Cavern Generator Pelton wheel Turbine U/G Transformer HV Cables 100MW LV BusBars Power Tunnel Max flow rate = 18.7m3/sec Static Head (604.3m) - Losses = Net Head Dam Intake tower Reservoir Aqueduct Glendoe HEP Scheme Spillway shaft PDF created with pdfFactory trial version www.pdffactory.com 2 Access Tunnel: Drilling and blasting of the access tunnel is well on target with more than half of the 1200 metre tunnel now excavated. Work will then begin carving out the power station cavern 250 metres below ground level, which will house the giant turbine and generator as shown in the diagram on the previous page. Aqueduct Tunnel: Meanwhile, at the other end of the project, work has started on the aqueduct tunnel, which will ultimately be used to feed water into the reservoir. The picture above shows work just beginning to form the portal, or entrance to the 7km tunnel. The PDF created with pdfFactory trial version www.pdffactory.com 3 tunnel is programmed for completion in the spring of 2008. Dam: Work is well underway excavating down to the foundation rock along approximately a third of the length of the 1000 metre dam. The picture below shows progress on the bottom outlet from the dam. This is at the base of the dam and will be used to release water from the reservoir into the River Tarff (just visible on the right of the picture) on the rare occasions when it would be necessary to drain the reservoir. PDF created with pdfFactory trial version www.pdffactory.com 4 Camp Site: Work is also well in hand for the second camp up near the dam. This will be used to accommodate staff working on the dam and aqueduct tunnel. Occupation of the camp will begin later this month. These updates are issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by email PDF created with pdfFactory trial version www.pdffactory.com 1 Glendoe Hydro Electric issue 7 October 2006 Tunnel Boring Machine (TBM): At the very end of last month Eliza Jane was finally commissioned on time and took the first tentative cuts at the rock face to begin her 6-month journey through the hill to complete the 2km tailrace tunnel. The photograph above shows the back of the machine as it prepares to disgorge the rock spoil on PDF created with pdfFactory trial version www.pdffactory.com 2 to the conveyor belt and out to the holding area. Once she is fully up to speed she is expected to produce at least 25 metres of finished tunnel every day. Also visible on the photograph is the ventilation duct through which huge fans suck in vital fresh air for the staff working deep in the tunnel. These fans have to operate round the clock and so that their noise isnt a nuisance for people in the surrounding area they have been located well inside the tunnel. Hochtief have just taken delivery of the first of several of these multi service vehicles, which have been purpose-built to supply equipment and materials into the tunnel. PDF created with pdfFactory trial version www.pdffactory.com 3 Conveyor Belt: The conveyor belt, which carries the rock out of the tunnel has also just been commissioned and will shortly be covered over in its corrugated iron housing. The photograph below shows the holding area up behind the main offices and camp where the rock will be stored before being used at various locations throughout the site. Cable Laying: Balfour Beatty have now left site having completed the first stage of the cable works but will be back probably towards the end of next year for the final stage. Meanwhile specialised contractors will shortly begin excavations to establish the ground conditions for the cable ducts under the canal and the River Oich. PDF created with pdfFactory trial version www.pdffactory.com 4 Dam: Work on the second camp area up at the dam site is progressing well with several of the buildings already up. The camp should be ready for occupation sometime next month. Over two hundred staff will eventually be working on the dam and the associated aqueduct of which a hundred and twenty or so will be housed in the camp. These updates are issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by email PDF created with pdfFactory trial version www.pdffactory.com 02.10.06 Kenyan athletes won both the men's and women's marathons at this year's Baxters Loch Ness Marathon and Festival of Running yesterday. Just eight seconds separated the first and second runners in the men's marathon, which took place along the south side of Loch Ness and on to the Inverness Queens Park Stadium. Zakary Kihara, of Kenya, beat last year's winner Simon Pride, of Fochabers, into second place with a time of two hours, 22 minutes and 17 seconds. Mr Pride, who also won the race in 2004, completed the course in two hours, 22 minutes and 25 seconds. Third was Jamie Reid, of Ronhill, Cambuslang, near Glasgow, in a time of two hours, 24 minutes and four seconds. A total of 5,600 runners of all ages and abilities took part in the day, sponsored by Baxters Food Group, putting this year's entry about 1,000 up on the previous record. The full marathon attracted 2,073 runners, while 2,450 took part in the Baxters River Ness 10k Run and there were almost 1,000 entries in the Baxters River Ness 5k Fun Run. The women's marathon was hotly contested, with Kenya's Hellen Cherono winning in a time of two hours, 46 minutes and 54 seconds. Second was Krystyna Kuta, of Poland, with two hours, 47 minutes and 30 seconds, followed by Jennifer Maclean, of City of Edinburgh Athletic Club, with two hours, 58 minutes and 57 seconds. Race director Malcolm Sutherland said the event not only attracted elite Scottish, international and club runners, but was massively popular with amateurs, joggers and people running for charity. Mr Sutherland said: "The event has been an outstanding success and the weather conditions tested all runners?. He said the event also provided a massive boost to the local economy. The most recent figures available show that £958,100 was spent on accommodation, food and activities during the 2004 festival I am pleased to announce a £20,000.00 upgrade at Loch Ness Gun Club in early October. This is a continuation of facility upgrades including new toilet block, new disabled access ramp to club house and a further £14000.00 of upgarding of equipment over the last year. This new upgrade is privately financed and is updating one of the Olympic Trap ranges at the ground. This will see only the second such range in Scotland, the other being in Ayrshire. Once completed the range will be completely automatic dispensing with the need of manual operation. This will significantly add to the facilities we currently have and expect a substantial increase in visitors and competitors to the ground at Bhlaraidh, Glenmoriston. We will be open this Saturday (23rd) for the Duncan Macdonell Memorial Shoot, 100 DTL and next Wednesday from 3pm to 7pm for a club practice and Saturday (30th) for coaching and practice with ex British Shooting Champion Mike Milne. Anyone is welcome when we are open and I am only too happy to personally show visitors and locals alike round the facilities. We will be closed during the month of October but will be open every Saturday from the 4th of November onwards. We also welcome anyone who hasnt shot before to come and give it a try with experienced coaches available every day apart from a Sunday by prior appointment. For more information I can be contacted on 01320 340341, 07770 800910 or dagillies@hotmail.com. The web address is www.lochnessgunclub.co.uk Regards David Gillies Director Loch Ness Gun Club Ltd Achlain Estates Limited Glenmoriston Inverness IV63 7YN tel: +44 (0) 1320 340341 fax: +44 (0) 1320 340255 email: david@achlainestates.co.uk website: www.achlainestates.co.uk 1 Glendoe Hydro Electric issue 6 September 2006 Traffic Management: The temporary traffic lights on the B862 will be removed in the near future and priority will return to traffic on the B862. There have however been a number of complaints by residents that traffic on the B862 and B851 has not only increased dramatically since the project began but also the standard of driving has caused concern. Highland Council has been monitoring the volume of traffic and will be releasing the figures shortly. In the meantime Hochtief has written to all their subcontractors reminding them of their contractual obligation to use the A82 as the main access to the site. Hochtief has also erected signs at critical locations on the B862 and B851 advising there is no access to the site from these roads. Tunnel Boring Machine (TBM): Work continues commissioning Eliza Jane and she is expected to start work in earnest at the end of September. Progress will depend on rock conditions but she should be able to get through somewhere in the region of 25 metres of finished tunnel a day. This will mean the 2km tailrace tunnel up to the cavern power station will be finished around March 2007. PDF created with pdfFactory trial version www.pdffactory.com 2 A further 12 months of boring through the mountain will be needed for the 6km headrace tunnel from the power station up to the dam. Conveyor Belt: The huge volume of rock that Eliza Jane throws out will be taken by conveyor belt up to the designated disposal area. The rock will be used for construction and future maintenance of the roads. Work is well under way with erecting the conveyor belt and the photograph below shows the belt as it passes below the B862. Cable Laying: Balfour Beatty have virtually completed the first stage of the cable works and will return in a year or so to install the 132,000 volt cable from the power station up to the existing PDF created with pdfFactory trial version www.pdffactory.com 3 Auchterawe substation. Detailed site investigations are being carried out to establish the ground conditions for the cable ducts under the canal and the River Oich. Dam: The rock for constructing the dam will be produced from a quarry currently being created near the dam site. A second work camp is also being established here for over a 100 staff who will be working on the dam and the aqueduct feeding water into the proposed reservoir. The photograph below shows progress with the new road up to the dam site. PDF created with pdfFactory trial version www.pdffactory.com 4 Community Event: This was held on 16 August in Kilchuimen Academy and over 120 locals visited the exhibition and heard progress on the project to date. Afterwards a number stayed on to ask questions and share in some light refreshments. The photograph below shows some of those who attended. These updates are issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by email PDF created with pdfFactory trial version www.pdffactory.com 1 Glendoe Hydro Electric issue 5 August 2006 Camp: The move up to the camp is almost complete with only the canteen to be re-sited, which should happen by the end of August. Of the 250 or so staff on site around a 100 are now resident in the camp. Hochtief operate a bus service for staff from the camp down to the village. Blasting: There have been a large number of complaints about the disturbance the blasting is causing in the village. Hochtief have explained that they try whenever possible not to blast between 11.00pm and 7.00am. However unfortunately there are occasions when it is not possible to avoid these times. When the charges have been set and there is a delay (for example because of a miss-fire) then they have no alternative for safety and other reasons but to carry through with the operation. The good news is that this particular blasting programme will be finished by mid August. PDF created with pdfFactory trial version www.pdffactory.com 2 Traffic Management: Work on the B862 from the bridge just beyond the Abbey up to the site entrance has now been completed. The road verges have been strengthened and a 30mph speed limit introduced between the camp entrance and beyond the entrance to the access tunnel. In addition some of the ditches have been cleared to improve drainage and also undergrowth has been cut back to improve sight lines. Tunnel Boring Machine (TBM): Eliza Jane has now been delivered to site and is currently being assembled ready to start drilling the tailrace tunnel in September. The huge scale of the machine can be grasped from the recent photograph below where the two men on top of it can just be made out. PDF created with pdfFactory trial version www.pdffactory.com 3 A large white gantry crane has also been assembled, which is visible from across Loch Ness and will be used to load heavy materials and equipment on to special multi-service vehicles to supply Eliza Jane. This crane, shown in the photograph below, will be removed when the tunnel is complete. Installation of the conveyor belt, which will be used to take the spoil from Eliza Jane up to the storage area behind the camp is also under way and will be ready to go for the end of August. Cable Laying: As mentioned in last months bulletin this first stage of the cable laying programme is almost complete. However during August a detailed site investigation will be carried PDF created with pdfFactory trial version www.pdffactory.com 4 out to establish the ground conditions for the cable ducts under the canal and the River Oich. Dam: Trial pits have now been excavated to establish the foundation conditions for the dam, which will be laid in August. The new road up to the dam site is almost finished and survey work is under way for the tunnels and aqueduct to supply the reservoir. Community Event: This has been planned for Wednesday, 16 August, starting at 5pm at Kilchuimen Academy. There will be an exhibition, followed by a presentation at around 7.30pm and the event will conclude with a canapι reception from 8pm. The event will be widely publicised locally and all local people will be welcome to attend. Communication: Hochtief have created a 24 hour Emergency Hotline Tel: 01456 450950 or if out of hours please call: 07867 973 926 or 07717 574 289 These updates are issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by email PDF created with pdfFactory trial version www.pdffactory.com Glendoe Hydro Electric Bulletin issue 4 July 2006 Camp: Some of the workforce have moved up to the camp and this will continue throughout the coming weeks. The move could however be delayed because of a problem with the building warrant. Recruitment: Hochtief took part in a Meet the Buyer workshop at the end of June. This was organised by Highlands & Islands Enterprise and enabled over 40 local contractors and suppliers to pitch their wares. Blasting: Surface blasting is now complete at the tailrace tunnel with the tunnel itself now reaching nearly 100 metres into the hillside. A large blast at 4.00am in the morning towards the end of June caused a number of complaints. The blast was exceptionally loud because it was at the point where the access and tailrace tunnels meet and so there was effectively double the size of blast expelled from the access tunnel. Cable Laying: Balfour Beatty Power Networks have completed the first stage of 33,000 volt and 11,000 volt cable laying i.e. from the Golf Course up to the site. The reinstatement of the track will be completed by mid July. The second stage will be to install ducts from the Golf Course up to the existing substation at Auchteraw, which should be complete by mid September. The crossing underneath the canal will be done using a directional drilling technique. Next year Balfour Beatty will return to install the 132,000 volt cable from the site through the ducts to Auchteraw Traffic Management: Part of the B862 road from the bridge up to the site has been widened to ease traffic congestion and will be tarred in early July. Once the road has been white-lined it should provide route for pedestrians. Communication: SSE are currently exploring setting up a dedicated website within the village and some way to make it available to visitors and residents alike. An A5 size 16-page colour brochure is also being published which will be available to visitors and residents to take away and will explain the project. Preparations are also under way for a visit to the site early in August. The invitation will be extended to all members of the local communities who will be able to meet members of the project team along with representatives of the Scottish Community Foundation who it is hoped will help with distribution of the Community Benefit Fund. Members of SSEs energy efficiency team will also be on hand to offer advice. At that time it is expected that the huge tunnel boring machine (TBM) will have been assembled and it may be possible for a lucky few to get a trip down to see it. The TBM has been named Eliza Jane following a competition among Kilchuimen Primary School pupils. Site Works: The new road up to the site of the dam is well under way and work on the dam itself is due to begin in August. The 33/11kV transformer was installed in mid-June and is currently undergoing tests prior to commissioning. The transformer will be used to supply power into the site but once the power station comes on stream in 2009 will be used to support the village distribution network and should ultimately allow removal of Markethill substation on the burial ground road. These updates will be issued monthly and if you are not already receiving them directly by email and would like to please contact douglas.gilchrist1@btopenworld.com or if you have any questions or concerns about the project you should contact Douglas Gilchrist, the Community Liaison Officer at 01463741322 or 07770408083 or by email
|
|